We present to you the key activities at the Anichi Resort & Spa construction site for August 2024:

  • Concrete pouring for the foundation at the entrance building has been completed, with ongoing installation of steel reinforcement and formwork for the walls. Similar preparations are underway in other areas of the building. On the lower floor and surrounding areas, masonry and plastering work is being carried out, while inside the building, electrical systems, ventilation and air conditioning systems, and fire safety measures are being installed.

  • Pipeline installation continues in buildings 1, 2, and 3.

  • Framework installation for drywall partitions and suspended ceilings has been completed in buildings 9 and 10, with ongoing work in building 8.

  • Tiling work is actively progressing in buildings 1, 2, and 10.

August 2024 Construction Progress:

 

August 2024 Construction Photo Gallery:

 

We invite investors to participate in the creation of the unique Anichi Resort & Spa project, located in one of the world’s most attractive regions. Investing in this project not only offers the opportunity to obtain Dominican citizenship but also provides prospects for long-term returns from premium real estate. To learn more about the benefits of second citizenship and investment opportunities, contact us today.