Take a quick look at our update from the construction site of Anichi Resort & Spa, located in Dominica. Works carried out in July 2021:

  • Entrance building: walls, columns and floor slabs casting of the ground floor, waterproofing of retaining walls and earthworks.
  • BOH building: plastering of exterior, general improvement of site drainage and earth levelling.
  • Other buildings: sunken slab waterproofing and filling of light weight concrete, water line testing and insulation, electrical wiring.